Oltmans Special Projects Division was hired to provide general contracting services as well as MEP and fire/life safety design-build services for this 2-level, 48,800 s.f., tenant improvement project located in a multi-story Class A office building. Prior to construction, the building was an empty shell with virtually no interior improvements.

A notable accomplishment was Oltmans’ ability to quickly adapt to project changes such as the truncated schedule. The original construction schedule was condensed from 12-weeks to just 60-days with no additional costs to the Client. Oltmans was able to push the subcontracting team to complete the project ahead of the truncated schedule.

The scope of the project included all new VAV zone boxes, ceilings, walls, doors, flooring and all finishes. The newly renovated floors featured offices, bull pen area, reception area, conference rooms, breakrooms, and kitchens.

Square Footage: 48,800 s.f.