The Moreno Valley Logistics Center is located a mile east of Interstate 215. Over the span of a ten-month construction schedule, Oltmans completed Building 1, a S-1/B, Type III-B, 1,331,763-s.f., concrete tilt-up shell on a 2,727,285 s.f. site area, including tenant improvements.

Associated improvements to the project site include surface parking areas, vehicle drive aisles, truck courts, utility infrastructure, landscaping, exterior lighting, signage, three water quality/detention basins, and street frontage improvements. The project includes a 300kW solar power system, ESFR K-28 fire sprinkler system, and an eight-inch thick slab.

Trailer Parking Lot

The second phase to the construction of the core & shell Moreno Valley Industrial Center, included construction of 271,618 s.f. of surface parking for trailer trucks.

The parking lot included a guard shack, three automated gates, 616-linear-feet of 14’ high concrete tilt-up screen walls, 1,848-linear-feet of tubular steel fencing, a detention basin, and associated site lighting.

Building Area: 1,332,000 s.f.

Trailer Parking Lot Area: 271,618 s.f.

Site Area: 2,727,000 s.f.